Two topics come up again and again on the PMI-RMP exam: calculating expected monetary value (EMV), and choosing the right risk response strategy. This guide explains both in plain English.

What is expected monetary value?

EMV puts a single money figure on an uncertain event by combining how likely it is with how much it would cost (or earn):

EMV = probability × impact

Threats have a negative impact, opportunities a positive one. Add the EMVs of several risks together to see the overall exposure.

Worked example

A construction project has identified two risks:

  • Threat: a 35% chance that a supplier delay costs $64,000. EMV = 0.35 × −$64,000 = −$22,400.
  • Opportunity: a 15% chance that a bulk discount saves $48,000. EMV = 0.15 × $48,000 = +$7,200.

Combined EMV = −22,400 + 7,200 = −$15,200. That figure can help set the size of a contingency reserve for these known risks.

EMV in decision trees

Decision trees use the same idea. For each option, multiply each possible outcome by its probability, add them up, and include the option's cost. Then compare the options: the one with the best EMV is usually the preferred choice — unless the organisation's risk appetite says a lower-risk option is worth more.

Responses to threats

StrategyWhat it meansExample
EscalateThe threat is outside the project's scope or the project manager's authority, so it goes to the right owner in the organisationA change in company policy affects the project
AvoidRemove the threat completely, e.g. by changing the planDrop an untested technology from scope
TransferShift ownership and impact to a third partyInsurance, warranties, fixed-price contracts
MitigateReduce the probability or impactExtra testing, a prototype, a second supplier
AcceptAcknowledge it; actively (set aside a contingency reserve) or passively (no action beyond monitoring)A small, unlikely risk

Responses to opportunities

StrategyWhat it meansExample
EscalateThe opportunity is outside the project's authority, so it goes to the right ownerA benefit that would serve the whole organisation
ExploitMake sure the opportunity definitely happensAssign your best people to finish early
SharePartner with a third party better able to capture itA joint venture
EnhanceIncrease its probability or impactAdd resources to raise the chance of an early finish
AcceptTake advantage if it happens, without actively pursuing itA possible but minor saving

Three terms to know

  • Residual risk: the risk that remains after a response is carried out.
  • Secondary risk: a new risk created by carrying out a response.
  • Contingency vs management reserve: contingency reserve covers identified risks ("known unknowns"); management reserve covers unidentified ones ("unknown unknowns").